Thursday, May 2, 2013

SFO BAY BRIDGE SECOND CROSSING, ENGINEERING CONSIDERATIONS


SFO BAY BRIDGE SECOND CROSSING
ENGINEERING CONSIDERATIONS

By Ronald F. Middlebrook, S.E. and Roumen V. Mladjov, S.E.

The new second crossing of the San Francisco – Oakland Bay Bridge is proposed to be built as a combination of a new West Crossing and a refurbished and reinforced structure salvaged from the abandoned existing structures of the East Crossing.

The New (2nd) West Crossing is proposed to consist of three structural parts each a double-decker to match the existing 1936 structure with five traffic lanes in each direction or with four traffic lanes plus a shoulder in each direction. Optionally there is an opportunity to use a wider deck to accommodate an additional lane to extend to San Francisco the bicycle/pedestrian lane currently included with the new East Crossing construction only between Oakland and Yerba Buena Island (YBI).  This would require new ground level bike lane transitions on YBI between the new West Crossing and the 2013 East Crossing.

1st Transition structure (San Francisco approach) with total length of 540 m (1,772 ft) on three or four continuous spans;
                                                                                                                                                                          
Suspention structure – with total length – 2,980 m (9,777 ft, or 1.85 mile) including:
Two side spans of 370 m (1,214 ft)
Two interior spans of 740 m (2,428 ft)
One Central/main span of 760 m(2,493ft)
 
Optionally, a Cable-Stayed system using the same spans as above should be studied and compared with the suspension bridge for selecting the more efficient cable-supported system (in cost, steel quantity and construction time).
The reasoning behind the above proposed spans is that the new West crossing structure should be in harmony with the existing iconic bridge and should not, in any case, overshadow it. While today’s suspension bridges are built with spans easily exceeding 1,000 m and even cable-stayed bridges have been built with spans greater than 1.000 m, the proposed spans of 740 to 760 meters are in the optimum range of the most efficient bridge structures for the two suggested systems.  In addition these spans are very close to the spans of the existing suspension bridge and should not inhibit navigation any more than it does.

The proposed alignment avoids a new tunnel on YBI. The east anchorage of this bridge would be a new pier just of the southern tip of YBI, which would also serve as the support of the west end of the 2nd Transition, described below.     
                        
Based on the average steel used for similar structures in the last 10 -12 years (maximum spans 760 m, average span 600 m) the estimated steel needed for a new suspension structure is in the range of 78,700 tons, and for a cable-stayed – 86,000 tons.  It is a known that the unit steel cost for a cable-stayed bridge is lower than the unit cost for a suspension bridge.

2nd Transition structure, near Yerba Buena Island, estimated total length 530 m (1,739 ft) on three or four continuous curved spans.  This 2nd transition structure will connect the new West and East crossing.

The total steel needed for the Second West Crossing is estimated as listed below:

1st Transition structure   (540 m)                                             8,800 tons
 
Suspension structure (2,980 m)                                             78,700 tons
 
Optional Cable-Stayed structure (2,980 m)                         (86,000 tons)
 
2nd Transition structure (530 m)                                              8,600 tons

TOTAL for 4,050 m Second West Crossing                         
 with Suspension structure                                      96,100 tons      
              
TOTAL for 4,050 m Second West Crossing                                
with Cable-Stayed structure                                  103,400 tons                                                               
 
The new West crossing should be designed at the highest level of today’s achievements in bridge engineering and construction using orthotropic decks, high strength steel and concrete, composite steel-concrete elements, using the best experience in long-span bridge engineering. The new structure should be designed as highly efficient in cost, use of material and construction time and should be used as an example for a new generation of bridges with emphasis on efficiency and economy.
 
The New (2nd) East Crossing  is proposed to be built using the refurbished and reinforced original East Crossing structures (all with the same spans as the original bridge). The idea is to reuse, for a “second bridge life”, the abandoned East crossing structures, slightly realigned on new foundations and piers. It will consist of:

The existing Cantilever Truss section, reinforced (for example) with “cable-stayed” type post tensioned system creating applied upward forces at the main span tips of the cantilevers, plus any necessary replacement or reinforcing of existing individual elements. The “cable-stayed” reinforcing could be prestressed to about 80-85% of the dead load reactions at the cantilever ends therefore relieving the existing cantilevered structure of about 60% of the total loads. Total length 736 m (2,416 ft)
 
Deep truss system with five spans by 153.6 m (504 ft), total length 768 m (2,520 ft).  One possible simple option for improving performance is to interconnect the five spans to form a continuous truss system reducing the demands on the steel members from 25 to 70%.
 
Double-deck truss system with 14 spans by 87.8 m (288 ft), total length 1,229 m (4,032 ft).  Similar to the deep truss system, providing continuity between the ends of the trusses may be the most efficient approach for strengthening this part of the existing structure.

The ten spans (single deck only, the eastbound lanes) of the Oakland landing, total length 327 m (1,073 ft) retrofitted as necessary.
 
A replacement of the existing old concrete deck of the abandoned structures with new, lighter, orthotropic deck (reducing the self weight of the bridge) should be studied as a valuable option for increasing the overall load capacity of the bridge and allowing less heavy equipment for the proposed re-alignment of the existing structures.

All of the spans of the original East Crossing should be re-assembled on, or moved on to new foundations and piers aligned to achieve a smooth traffic transition from the new West Crossing to the realigned East Crossing.  
The Oakland landing and part of the 14 – 288 ft spans should remain as close as possible to the existing alignment.

The total estimate for the steel needed for the Second East Crossing is: 

- New substructure – piers                                                     6,500 tons
 
- New elements for refurbishing the existing spans            12,000 tons
 
- Remaining original (existing) structures                           48,500 tons
 
- TOTAL for the Second East Crossing                           67,000 tons
                                (This means only 18,500 tons for new structure)

The total steel quantities for the proposed Second Crossing (West and East) are estimated as:
- 163,100 tons (including 115,000 tons new structures) for the suspension option, or
- 170,400 tons (including 122,000 tons new structures) for the cable-stayed option.  

The primary advantages of a SFO Bay Bridge 2nd Crossing as proposed are:

  •      Engaging some of  the best engineers and builders through an open competition/design-build project approach;
  •      Effectively increasing the traffic capacity by 80-85% of the capacity expected for the newly renovated Bridge; (2013;
  •      A reserve link between San Francisco and Oakland; extremely important in case of a serious accident, or  other damage (to the 2013 bridge);
  •      Preserving and reusing an iconic historic bridge structure considered as one of the highest achievements in engineering;
  •      Significantly less new steel and structures compared with any system of bridge, because of  the reuse of most of the existing structures of the original East Crossing;
  •      Greatly reduced construction time;
  •      Significantly lower cost than the 2013 East Crossing replacement;
  •      Significantly more environmentally friendly than any entirely new structure (smaller carbon footprint);
  •      The experience gained from this project could serve as new approaches for renovation of many old existing bridges in the country (24% of the existing bridges in the country, or 144,000 bridges are listed as deficient based on December 2011 data.
Note: All the steel quantities above are in metric tons (one metric ton = 1.102 U.S. tons, or equal to 2,205 lbs).

No comments:

Post a Comment