Monday, May 6, 2013

San Francisco - Oakland Bay Bridge Second Crossing



Ronald F. MIDDLEBROOK             
Structural Engineer                                                                                        
Middlebrook + Louie (retired)
Past President - SEAONC                                                                            
San Francisco, @Sonoma, CA, USA                             
ronfranco@gmail.com

Roumen V. MLADJOV
Structural Engineer
Louie International
San Francisco, CA, USA
rmladjov@louieintl.com

Summary

Built in the 1930’s, the San Francisco-Oakland Bay Bridge reached its capacity to adequately carry traffic in the 1980’s. After the 1989 Loma Prieta earthquake, the bridge’s West crossing was reinforced and its East crossing is currently being replaced in its entirety (Fig.1). Despite these improvements, the traffic capacity of Northern California’s busiest highway link remains unchanged -- clearly inadequate for the current demands of Bay Area Traffic. The authors discuss a creative alternative to the proposed demolition plans for the soon-to-be-retired East crossing elements: reusing these structures as part of a new, separate crossing. This paper describes several potential benefits of relocating and converting these existing steel structures into a new bridge, including nearly doubling current traffic capacity, as well as significant time/cost savings.

 Keywords: bridge, retrofitting, reinforcing, reuse, traffic, Oakland, San Francisco, Loma Prieta.


Fig. 1. Bay Bridge with New East Crossing (under construction)


  1. Introduction, Historic Significance

 The San Francisco-Oakland Bay Bridge opened to traffic in 1936. It connects San Francisco and Oakland, and is the busiest vehicular link in Northern California.

 The bridge is actually several bridges with distinctly different structural systems, strung together to form about a 13,7 km cross-bay roadway (7,1 km over water). West crossing: the 3140 m crossing from San Francisco to Yerba Buena Island (YBI) includes a twin suspension bridge with central spans of 704 m (Fig. 2). YBI segment: the 549 m Yerba Buena Island (YBI) segment features a tunnel and short concrete viaduct. East crossing: the 3417 m crossing from YBI to Oakland consists of several different steel truss systems: four short, (approx. 88 m) steel truss spans on YBI followed by the 738 m long cantilever truss structure (Fig. 3), then five deep through-truss spans at 155 m, fourteen deck-truss spans at 88 m, and the remainder on simple land-based steel structures.

 The original Bay Bridge is one of the grandest achievements of the American Art of bridge engineering, and is clearly important from a historic standpoint. At the time of completion, the bridge was the longest bridge in the world – 13,7 km, including approaches. Among the bridges of the world at that time, it featured the second longest suspension span (704 m), the third longest cantilever truss span (427 m), the deepest pier foundation (74 m below water surface at low tide), and the largest bored tunnel. The West crossing was the only major bridge with two consecutive suspension spans.

 The bridge, with its three major segments, is listed on the National Register of Historic Places (NRHP). The Register’s comment is: “One of the largest and most important historic bridges in the country”. In addition to its place on the NRHP, the bridge received accolades from former President Herbert Hoover, speaking at the ground-breaking ceremony in 1933: “This marks the physical beginning of the greatest bridge yet erected by the human race.” Hoover, who was originally a mining engineer, had followed the development of the design of the bridge during his presidency. He was particularly interested in its effect on unemployment in trying times—the Great Depression.

 The entire bridge deserves its exalted historic credentials, from the graceful sweep of the West crossing suspension structure, through the YBI tunnel and viaduct, to the steel Cantilever Truss section, to the through-truss and deck-truss spans.

 The bridge was built in just 3½ years, at a cost then estimated at $78 million. It was, and still is, one of the greatest engineering achievements of the 20th century.


 
 
    Fig. 2. West crossing
 


Fig. 3. East crossing (currently being replaced)
 
 2. General details, design & construction 

The Bay Bridge is a double decker. The original design featured 6 automobile lanes on the top deck – 3 lanes in each direction. The bottom deck provided 3 truck lanes and 2 lanes (one in each direction) for an interurban commuter train. Around 1960, the arrangement was converted to five eastbound lanes of traffic on the lower deck and five westbound lanes on the upper deck.

 The Bay Bridge was designed and built using state-of-the-art techniques available in the 1930’s. For example, the engineers specified the highest strength steel available for critical elements of the structures. Nickel (Grade 380 MPa) and silicon steel (Grade 311 MPa) for the East crossing making up 62% of the total steel used there and 72% of the Cantilever section. Even the carbon steel used in this bridge was higher strength (Grade 255 MPa) than normal. High-strength cable steel (Grade 828 MPa) was specified for the West crossing suspension cables.

 The entire bridge required 151 593 tons of structural steel. [1]

 The Bay Bridge, and its neighbor, the Golden Gate Bridge (completed at about the same time) represent the culmination of more than 100 years of development of bridge engineering and construction in the United States. To fully appreciate the achievement of completing the construction in just 3½ years, consider the technical level of construction at the time. In addition to the lack of modern devices – heavy construction equipment, vehicles, cranes, etc. - all steel connections were made using rivets, requiring much more time and labor than modern high strength bolting and welding. Compare this achievement with the 12 years it is taking to build the current replacement bridge just for the East crossing!

 Amazingly, the 151 593 tons of steel used for the entire Bay Bridge in 1936 is less than the tonnage Caltrans reported for building just the superstructure of the new East crossing replacement [2]. A testament to the wisdom of the design for the Bay Bridge West crossing is that, 62 years later, Japanese engineers chose a very similar design for the towers of the longest bridge span in the world: the Akashi-Kaikyo (or Pearl) Bridge.



   Fig. 4. Local damage to the East Crossing 


 3. Loma Prieta earthquake (1989)

 The bridge’s East crossing was locally damaged during the Loma Prieta earthquake of 1989. A 15 m section of the top deck slipped off its support at an expansion joint; that end of the section collapsed onto the lower deck (Fig.4). One motorist was killed.

 It was subsequently decided to replace the entire East crossing. Caltrans (California’s Department of Transportation) dubbed the project an Earthquake Safety project, an important decision because it meant only the pre-existing traffic capacity would be restored. After 7-8 years of discussion, planning and design, construction on the new East crossing finally began in January 2002. The current estimate for project completion is October 2013.

 4. West crossing improvements and East crossing replacement 

The West crossing (and its approach) underwent seismic improvements in a 5-year project beginning in 1999, at a reported cost of approximately $759 million. The improvements included massive rollers installed between the roadway and bridge supports and 96 new viscous dampers inserted at critical points to allow movement. The bridge’s twin suspension spans were strengthened by adding new steel plates and replacing half a million original rivets with almost twice that many high strength bolts. New bracing was added under both decks and all of the “laced” truss diagonals connecting the upper and lower road decks were replaced. In total about 7710 tons of structural steel was added.

 The East crossing replacement is currently under construction. It consists of a single tower self-anchored suspension span and a 14 span (140 m. each) concrete skyway. The new crossing has added shoulders and a bicycle lane. (Since there is no bicycle lane on the West crossing, it will not be possible to bike the entire length of the bridge). The cost of replacing the East crossing is $6 417 M. Current plans are to demolish all of the original East crossing structures from YBI to Oakland, and presumably recycle whatever possible. Demolition is currently estimated to cost at least $280 million. [2], [3]

 5. Traffic capacity and population demographics 

With only 5 traffic lanes in each direction, traffic movement is greatly compromised, especially during commute hours.

 In 1936 the Bay Area population was about 1 650 000. By 1990 it was about 6 024 000 and by 2010 it was 7 150 000. The projected population for 2025 is 8 880 000 (47% greater than in 1990).

 Traffic growth has been even more rapid. When the bridge originally opened in 1936, the traffic equivalent was 50 000 vehicles. By the late 1990’s, this critical highway link carried about 280 000 vehicles on an average day. So the growth in demand has increased nearly 6-fold over the past 75 years.

 Currently during commute hours it can take up to 30 minutes to drive the 7,1 km (from water’s edge to water’s edge) across the bridge. That’s 14 km/h, and sometimes it’s worse, especially if there is an accident on the bridge.

 The idea of supplementing traffic capacity across the bay is not new. Numerous studies over the past 60 years have been conducted for new crossings (both bridges and tunnels). None of these studies were pursued, for environmental, political, cost and other reasons. However, these efforts show a great deal of continuing interest in reducing the pressure on cross bay traffic.

 6. So what have we gained? 

After more than 17 years of planning, design and construction in connection with this new East crossing, along with the improvements to the West crossing described above, we have a seismically improved, 13,7 km long bridge (at a total cost over $7 billion). The entire Bay Bridge remains restricted to five vehicular traffic lanes, essentially as it was when it was born in 1936. The inadequacy to handle traffic demand was well known even when the new East crossing replacement was being designed in the late 1990’s. And as time goes by, the problem only gets worse!

 7. Proposed plans to increase traffic capacity 

Seeking a rational solution for this “problem”, some of the possibilities are:

 • Expanding BART’s (Bay Area Rapid Transit’s) underwater, cross-bay tunnel. BART has already reached maximum capacity of its twin tube system during peak commute times. Enlarging the underwater portion (and the above ground track system) seems unrealistic.

 • Adding more ferries. The Bay Bridge ended the ferry system era long ago. And ferries imply more automobiles to get to and from the water’s edge. Quite impractical.

 • Adding a second bridge parallel to the existing Bay Bridge, a more practical idea already proven in other cities around the world (Fig. 5).

 Considering these limited options, a second bridge seems to be the most logical approach to solve the restricted capacity of the existing bridge. And, given the fact that the replacement of the old East crossing structure is nearing completion, now is the time to begin planning and designing a completely new 2nd SFO Bay Bridge alongside the present one using the retrofitted, old East crossing structures. There are two major parts to this proposal:

 • The efficient retrofitting and realignment of the original, historic East crossing structures.

• The design and construction of a new West crossing, alongside and complementing the existing suspension bridge.


 
    Fig. 5. Existing and proposed second bridge

 8. New East crossing (second bridge) 

The current East crossing replacement project, now nearing completion, includes about $280 million for demolition of the replaced original steel structures. With the exception of the local damage caused by the ’89 Loma Prieta earthquake, the original structure has served well for 76 years carrying ever increasing volumes of traffic.

 The most questionable elements of the original (1936) East crossing are the foundations supporting most of the piers. These are timber piles driven into questionable soil and should not be considered safe for reuse. It is believed, however, that the idea of salvaging the 55 000 tons of already fabricated structures is a worthy one. The best option for reuse of the existing steel structures would be to build new foundations and piers alongside the current ones, barging and lifting or sliding the existing superstructure on to the new substructure and then reinforcing the existing superstructure to meet current codes.

 
Fig. 6. Old truss spans – concept for creating continuity

 Even if some of the existing structures need to be strengthened or reinforced, there is a good deal of value seen in the reuse of that steel, not to mention the possibility of converting significant demolition costs to a positive use – that of creating added bridge traffic capacity. In contrast to past studies, this proposal differs in that it looks to take advantage of the “abandoned” East crossing structures by retrofitting and reusing them. This represents some 55 000 t of fabricated steel that served very well for decades, and is doing so currently. Coupled with eliminating a good portion of the $280 million demolition budget, this could easily represent in the range of $500 million “in the bank” to be credited to construction of the new SFO Bay Bridge second crossing.

 There are various options for increasing the structural capacity of the systems involved. One method is to interconnect the adjacent simple spans, converting them to a continuous system (Fig.6). Members can be strengthened by a judicious addition of plates, channels or other shapes to the existing members, connecting them with bolts and/or welds. If necessary, compromised rivets can be replaced with high strength bolts, as in the West crossing retrofit.



Fig. 7. Cantilever truss section – reinforcing cable-stayed system

 An interesting option would be to add a cable-stayed type of reinforcement system to the Cantilever truss section introducing “up-lift” forces at the tips of the cantilever arms (Fig.7). Another ingenious way to “increase” capacity is to reduce dead load by replacing existing heavy reinforced concrete slabs with lighter systems such as orthotropic steel decks. This approach was used very successfully in the early 1980’s on the redecking of the Golden Gate Bridge. This can reduce deck dead loads by up to 50-60 percent, “buying” extra structural capacity or otherwise relieving overstress situations. This technique would also make foundations more economical to construct. Of course, combinations of such approaches would be in order. It is recognized that the use of orthotropic steel decks and other “lightening” techniques would require demolition of the concrete slabs now existing on the structures planned for demolition (approx. 102 000 sq. m of 160 mm slabs) thus reducing the potential savings from foregoing demolition. But the other benefits, such as having to deal with much lighter elements to be relocated, may well more than offset this issue. It is obviously very important that decisions be made and initial activities undertaken before the afore-mentioned demolition is initiated. That demolition is scheduled to begin in late 2013.

 9. New West crossing (second bridge) 

It is envisioned that the new West crossing would be a double decker like its neighbor so that it would “flange up” with the retrofitted (old) East crossing. That would mean it would have 5 lanes in each direction (or 4 lanes plus a shoulder) - the same width as the retrofitted East crossing. One scenario would feature twin suspension structures placed end to end from San Francisco to YBI very similar to the existing West crossing, but with two main spans of approximately 740 m, one central span of approximately 760 m and two side spans of 370 m. A central anchorage separating the twin bridges as in the 1936 bridge probably would not be necessary. Using the sophisticated analytical tools available to today’s engineers, it is felt the bridge can be designed and built without a central anchorage.

 While the original bridge featured a tunnel and viaduct through Yerba Buena Island separating the West and East crossings, the idea for the new bridge would be to create a pier near the southern tip of YBI. This pier would serve a combined function: anchorage for the east end of the new West crossing and support for the west end of a new, slightly curved, transition section between the pier and the west end of the retrofitted, relocated cantilever truss structure. 

An alternative to the above could be a cable-stayed bridge with similar spans. There may be other solutions, however, suspension and cable-stayed designs are the only ones that have been shown to reasonably span farther than 700 m. Consideration of other systems would likely require shorter spans necessitating more supports. This bridge should be designed to the highest level of today’s achievements in bridge engineering and construction using all modern technical ingenuity including orthotropic decks, high strength steel and concrete, composite steel/concrete and the like. It is the authors’ strong opinion, the way to achieve the best result in terms of beauty, efficiency, cost optimization and construction time is to invite international concept competition by the best bridge designers, worldwide. The winner of such a competition should be invited to participate in design-build competitions for the elements of the project.

 Fig. 8. Traffic lane concept for second bridge


 10. Discussions, Final Comments and Conclusions 

 Because of the relentless increase of population in the San Francisco Bay Area, and the resulting pressure on traffic crossing the Bay, it is inevitable that a new bridge will be needed to relieve that congestion. The abandonment of the old East crossing offers an opportunity to double, or nearly double, the capacity of the renovated SFO Bay Bridge. This paper lays the ground work for doing that cost effectively by realigning and retrofitting the 55 000 t of structural steel destined for abandonment and demolition, sitting out there alongside the new and reconditioned bridge. It has been demonstrated here how this could be done. But decision making and planning must begin very soon—especially the decision not to demolish the steel of the old East crossing.

 Advantages of the proposed Second Bay Bridge crossing include the following points:

 1. It will resolve the extreme traffic congestion problems associated with the original 1936 and improved current bridge, whose capacity has remained essentially the same for 76 years.

2. With four or five traffic lanes in each direction, the Second crossing will increase traffic capacity between San Francisco and Oakland by 80% to 100% (Fig.8). (Note: several options exist; 4 or 5 traffic lanes, plus a shoulder and/or a bicycle lane with the ability to adjust structural capacity by using orthotropic decks, etc.).

3. It will provide reserve crossing capacity should unforeseen problems such as serious accidents, earthquake or other damage, occur.

4. It will redistribute traffic flow within San Francisco by way of more entry and exit approaches, reusing previous routes from the removed in the 1990’s Interstate 280 to the Embarcadero.

5. It will greatly reduce the time required to cross the Bay especially in peak traffic hours.

 6. It will result in environmental savings from fuel saved by reducing “stop and go” traffic during commute hours.

7. It will result in environmental savings by the reuse of 55 000 tons of steel bridge structures – by reducing the need to produce, manufacture and transport this quantity of new steel.

8. It can result in the possibility for bicyclists to ride from San Francisco to Oakland and vice versa.

9. The large scale reuse of the existing East crossing structures will help in the development of pioneering techniques to be used for the retrofitting of many of the 150 000 deficient bridges in the U.S.

10. It will capitalize on converting demolition costs to new construction, and reusing already fabricated structures to the tune of $500 million or more.
11. With the ingenuity required to adapt the older structures to today’s requirements and the anticipated high level of design criteria and modern technique for the new West crossing, it will contribute to the reawakening of the Art of American Bridge Engineering.

 11. References 
[1] UNITED STATES STEEL, “The San Francisco – Oakland Bay Bridge”, 1936
[2] CALIFORNIA DEPARTMENT OF TRANSPORTATION, Bay Bridge Project / Fact Sheets, baybridgeinfo.org
[3] CALTRANS “2nd Quarter Report, 2012”, www.dot.ca.gov/baybridge/2012-2QReport.pdf









Thursday, May 2, 2013

Bay Bridge Population - Traffic


SFO BAY BRIDGE SECOND CROSSING, ENGINEERING CONSIDERATIONS


SFO BAY BRIDGE SECOND CROSSING
ENGINEERING CONSIDERATIONS

By Ronald F. Middlebrook, S.E. and Roumen V. Mladjov, S.E.

The new second crossing of the San Francisco – Oakland Bay Bridge is proposed to be built as a combination of a new West Crossing and a refurbished and reinforced structure salvaged from the abandoned existing structures of the East Crossing.

The New (2nd) West Crossing is proposed to consist of three structural parts each a double-decker to match the existing 1936 structure with five traffic lanes in each direction or with four traffic lanes plus a shoulder in each direction. Optionally there is an opportunity to use a wider deck to accommodate an additional lane to extend to San Francisco the bicycle/pedestrian lane currently included with the new East Crossing construction only between Oakland and Yerba Buena Island (YBI).  This would require new ground level bike lane transitions on YBI between the new West Crossing and the 2013 East Crossing.

1st Transition structure (San Francisco approach) with total length of 540 m (1,772 ft) on three or four continuous spans;
                                                                                                                                                                          
Suspention structure – with total length – 2,980 m (9,777 ft, or 1.85 mile) including:
Two side spans of 370 m (1,214 ft)
Two interior spans of 740 m (2,428 ft)
One Central/main span of 760 m(2,493ft)
 
Optionally, a Cable-Stayed system using the same spans as above should be studied and compared with the suspension bridge for selecting the more efficient cable-supported system (in cost, steel quantity and construction time).
The reasoning behind the above proposed spans is that the new West crossing structure should be in harmony with the existing iconic bridge and should not, in any case, overshadow it. While today’s suspension bridges are built with spans easily exceeding 1,000 m and even cable-stayed bridges have been built with spans greater than 1.000 m, the proposed spans of 740 to 760 meters are in the optimum range of the most efficient bridge structures for the two suggested systems.  In addition these spans are very close to the spans of the existing suspension bridge and should not inhibit navigation any more than it does.

The proposed alignment avoids a new tunnel on YBI. The east anchorage of this bridge would be a new pier just of the southern tip of YBI, which would also serve as the support of the west end of the 2nd Transition, described below.     
                        
Based on the average steel used for similar structures in the last 10 -12 years (maximum spans 760 m, average span 600 m) the estimated steel needed for a new suspension structure is in the range of 78,700 tons, and for a cable-stayed – 86,000 tons.  It is a known that the unit steel cost for a cable-stayed bridge is lower than the unit cost for a suspension bridge.

2nd Transition structure, near Yerba Buena Island, estimated total length 530 m (1,739 ft) on three or four continuous curved spans.  This 2nd transition structure will connect the new West and East crossing.

The total steel needed for the Second West Crossing is estimated as listed below:

1st Transition structure   (540 m)                                             8,800 tons
 
Suspension structure (2,980 m)                                             78,700 tons
 
Optional Cable-Stayed structure (2,980 m)                         (86,000 tons)
 
2nd Transition structure (530 m)                                              8,600 tons

TOTAL for 4,050 m Second West Crossing                         
 with Suspension structure                                      96,100 tons      
              
TOTAL for 4,050 m Second West Crossing                                
with Cable-Stayed structure                                  103,400 tons                                                               
 
The new West crossing should be designed at the highest level of today’s achievements in bridge engineering and construction using orthotropic decks, high strength steel and concrete, composite steel-concrete elements, using the best experience in long-span bridge engineering. The new structure should be designed as highly efficient in cost, use of material and construction time and should be used as an example for a new generation of bridges with emphasis on efficiency and economy.
 
The New (2nd) East Crossing  is proposed to be built using the refurbished and reinforced original East Crossing structures (all with the same spans as the original bridge). The idea is to reuse, for a “second bridge life”, the abandoned East crossing structures, slightly realigned on new foundations and piers. It will consist of:

The existing Cantilever Truss section, reinforced (for example) with “cable-stayed” type post tensioned system creating applied upward forces at the main span tips of the cantilevers, plus any necessary replacement or reinforcing of existing individual elements. The “cable-stayed” reinforcing could be prestressed to about 80-85% of the dead load reactions at the cantilever ends therefore relieving the existing cantilevered structure of about 60% of the total loads. Total length 736 m (2,416 ft)
 
Deep truss system with five spans by 153.6 m (504 ft), total length 768 m (2,520 ft).  One possible simple option for improving performance is to interconnect the five spans to form a continuous truss system reducing the demands on the steel members from 25 to 70%.
 
Double-deck truss system with 14 spans by 87.8 m (288 ft), total length 1,229 m (4,032 ft).  Similar to the deep truss system, providing continuity between the ends of the trusses may be the most efficient approach for strengthening this part of the existing structure.

The ten spans (single deck only, the eastbound lanes) of the Oakland landing, total length 327 m (1,073 ft) retrofitted as necessary.
 
A replacement of the existing old concrete deck of the abandoned structures with new, lighter, orthotropic deck (reducing the self weight of the bridge) should be studied as a valuable option for increasing the overall load capacity of the bridge and allowing less heavy equipment for the proposed re-alignment of the existing structures.

All of the spans of the original East Crossing should be re-assembled on, or moved on to new foundations and piers aligned to achieve a smooth traffic transition from the new West Crossing to the realigned East Crossing.  
The Oakland landing and part of the 14 – 288 ft spans should remain as close as possible to the existing alignment.

The total estimate for the steel needed for the Second East Crossing is: 

- New substructure – piers                                                     6,500 tons
 
- New elements for refurbishing the existing spans            12,000 tons
 
- Remaining original (existing) structures                           48,500 tons
 
- TOTAL for the Second East Crossing                           67,000 tons
                                (This means only 18,500 tons for new structure)

The total steel quantities for the proposed Second Crossing (West and East) are estimated as:
- 163,100 tons (including 115,000 tons new structures) for the suspension option, or
- 170,400 tons (including 122,000 tons new structures) for the cable-stayed option.  

The primary advantages of a SFO Bay Bridge 2nd Crossing as proposed are:

  •      Engaging some of  the best engineers and builders through an open competition/design-build project approach;
  •      Effectively increasing the traffic capacity by 80-85% of the capacity expected for the newly renovated Bridge; (2013;
  •      A reserve link between San Francisco and Oakland; extremely important in case of a serious accident, or  other damage (to the 2013 bridge);
  •      Preserving and reusing an iconic historic bridge structure considered as one of the highest achievements in engineering;
  •      Significantly less new steel and structures compared with any system of bridge, because of  the reuse of most of the existing structures of the original East Crossing;
  •      Greatly reduced construction time;
  •      Significantly lower cost than the 2013 East Crossing replacement;
  •      Significantly more environmentally friendly than any entirely new structure (smaller carbon footprint);
  •      The experience gained from this project could serve as new approaches for renovation of many old existing bridges in the country (24% of the existing bridges in the country, or 144,000 bridges are listed as deficient based on December 2011 data.
Note: All the steel quantities above are in metric tons (one metric ton = 1.102 U.S. tons, or equal to 2,205 lbs).

Save The Bay Bridge - International IABSE Conference, Rotterdam May 6 - 8, 2013

Introduction to SFO Bay Bridge Second Crossing



Feasibility Study Introduction
Ronald F. Middlebrook, S.E., Roumen V. Mladjov, S.E.


CURRENT SITUATION – the existing SFO Bay Bridge was completed in 1936.  It was then, and still is, one of the grandest engineering achievements in the Art of Bridge Engineering. The Bay Bridge, and its neighbor, the Golden Gate Bridge (completed at about the same time) represented the culmination of more than 100 years of development of bridge engineering and construction in the United States.  Traffic increased to an average 280,000 vehicles daily in the early 1990’s creating heavy congestion at peak commute hours.  The East Crossing (from Yerba Buena Island (YBI) to Oakland suffered local damage during the ’89 Loma Prieta earthquake.  In the mid-1990’s, Bay Area officials decided the East Crossing should be replaced.  The project was termed a seismic safety replacement of the East Crossing which meant only the earlier existing capacity could be replaced.  Construction started in 2002 and is scheduled for completion in late 2013.  After more than $7 billion spent and 12 years of construction the Bay Bridge will not have a single additional lane to relieve the congestion, already intolerable in the 1990’s.  The relentless increase of Bay Area population only makes congestion worse.

GOAL – the primary goal is to improve vehicle traffic capacity of this major Bay crossing between San Francisco and Oakland.  This proposal would increase that capacity by 80%, from 5 lanes to a total of 9 lanes in each direction.

THE SOLUTION – is to build a second crossing approximately parallel to the existing bridge on the south-east side of the current alignment. The west span should be a new bridge in harmony with the existing suspension bridge; the east span should be the abandoned existing structures retrofitted and relocated on to new foundations near the current alignment.

SAVING THE EXISTING EAST CROSSING OF THE BAY BRIDGE; AN HISTORIC LANDMARK – It is important to save and reuse the original east crossing of the bridge; otherwise to be demolished.  These structures are a symbol of the greatest era of American development, representing the structural types mostly used in building North America’s infrastructure in the 19th and first part of the 20th century. There are more than 23,000 historic truss bridges in the U.S.

AEsthetic Considerations -- The exposed steel typical for bridge crossings may not be largely accepted as classic, beautiful architecture, however the steel truss structures of the entire bridge are similar to the structures of several great, iconic bridges such as the Brooklyn and George Washington Bridges in New York, the Quebec Bridge, and the Sidney Harbor Bridge.
The truss type steel framing is beautiful; its forms are purely functional following the structural demand.  It reminds one of the famous Eiffel Tower, a structure much criticized at the time of its construction, but later acclaimed as one of the World’s top engineering and architectural achievements, becoming the symbol of Paris and of France.

STRENGTHENING AND REFURBISHING THE EXISTING EAST SPAN -- The best saving of an historic bridge is as a reuse or replacement bridge.  Often the strengthening consists of reinforcing all elements that are found not adequate for current code demands.  Occasionally, a more effective approach involves adding members to create continuity between structural elements.  For reuse of the original East crossing structures for the proposed Second crossing, the most efficient approach may be a combination of both, that is creating continuity between the ends of existing trusses and strengthening or replacement of individual elements found to be deficient.
Both types of truss spans, through truss and deck truss, can be easily transformed to continuous truss systems using four to five bays by adding new verticals and top chord elements at the supports.  This will automatically reduce the strength demand at the bays representing about 75 – 80% of the span lengths.

The cantilever truss structure can be strengthened by using post-tensioning to impose reversed tension/compression axial forces in the main bridge elements. A cable-stayed system seems an appropriate option for such modification.  This approach can relieve the dead load stresses in the existing structure by up to 75%.
A third way to “buy back” capacity is to reduce dead load.  These existing structures have 6” or 6 ½” reinforced concrete slabs as deck elements.  Removing these slabs and replacing them with a lighter deck system such as a steel orthotropic deck system can provide considerable new excess capacity for the existing systems.

MINIMUM GOAL – to receive meaningful, extended endorsement from the engineering and architectural professional organizations, the historic preservation societies and the media.

MAXIMUM GOAL – to gain strong public sympathy for the idea of building a new 2nd Crossing using the “retired” structures of the old East crossing and getting those feelings to the decision makers, the Governor and other State of California authorities, through such entities as ASCE, AISC, NSBA, SEAONC, AIA and the California Historic Society.

CHALLENGING PROJECT – accomplishing the idea for a Second Bay Bridge crossing is a very challenging task, but by far not equal to the problems our predecessors had to overcome some 80 years ago, designing and building simultaneously the Bay Bridge and the Golden Gate Bridge during the Great Depression. This project is completely within the capability of American engineers and builders; the only challenge is to persuade the Federal and State transportation authorities to start working immediately on the planning and design for the project.

PROGRAM for DEVELOPING and PROMOTING the IDEA -- All options to promote the idea should be used – articles, project web-site, presentations on professional conferences, publication materials in the media, including professional magazines, newspapers, TV information and interviews, public press-conferences, meetings and discussions with California transportation authorities, letters to the Governor of California and to the appropriate state government authorities.