SavetheBayBridge . com
Monday, August 19, 2013
Save the Bay Bridge
Save the 1936 East Span of the SFO Bay Bridge and reuse it to build the Eastern Span of a New San Francisco-Oakland Second Bay Bridge Crossing
Sunday, August 18, 2013
San Francisco - Oakland Bay Bridge Second Crossing. Paper
San Francisco - Oakland
Bay Bridge Second Crossing. A
Feasibility Study
Ronald F. MIDDLEBROOK
Roumen
V. MLADJOV
Structural
Engineer Structural
Engineer
Middlebrook
+ Louie (retired) Louie
International
Past
President - SEAONC San
Francisco, CA, USA
San
Francisco & Sonoma, CA, USA rmladjov@louieintl.com
Introduction
Built in the 1930’s, the San Francisco-Oakland Bay
Bridge reached its capacity to adequately carry traffic in the 1980’s. After the 1989 Loma Prieta earthquake, the
bridge’s West crossing was reinforced and its East crossing is currently being
replaced in its entirety. Despite these
improvements, the traffic capacity of Northern California’s busiest highway
link remains unchanged -- clearly inadequate for the current demands of Bay
Area Traffic. The authors discuss a creative alternative to the proposed demolition
plans for the soon-to-be-retired East crossing elements: reusing these
structures as part of a new, separate crossing.
This paper describes several potential benefits of relocating and
converting these existing steel structures into a new bridge, including nearly
doubling current traffic capacity, as well as significant time/cost savings.
Keywords: bridge,
retrofitting, reinforcing, reuse, traffic, Oakland, San Francisco, Loma Prieta.
Fig. 1. Bay Bridge with New East Crossing (under construction)
1. General Information, Historic Significance
1. General Information, Historic Significance
The San Francisco-Oakland Bay Bridge opened to
traffic in 1936. It connects San
Francisco and Oakland, and is the busiest vehicular link in Northern
California.
The bridge is actually several bridges with
distinctly different structural systems, strung together to form about a 13,7
km cross-bay roadway (7,1 km over water).
West crossing: the 3140 m crossing from San Francisco to Yerba
Buena Island (YBI) includes a twin suspension bridge with central spans of 704
m (Fig. 2). YBI segment: the 549
m Yerba Buena Island (YBI) segment features a tunnel and short concrete
viaduct. East crossing: the 3417
m crossing from YBI to Oakland consists of several different steel truss systems:
four short, (approx. 88 m) steel truss spans on YBI followed by the 738 m long
cantilever truss structure (Fig. 3), then five deep through-truss spans at 155
m, fourteen deck-truss spans at 88 m, and the remainder on simple land-based
steel structures.
The original Bay Bridge is one of the grandest
achievements of the American Art of bridge engineering, and is clearly
important from a historic standpoint. At
the time of completion, the bridge was the longest bridge in the world – 13,7
km, including approaches. Among the
bridges of the world at that time, it featured the second longest suspension
span (704 m), the third longest cantilever truss span (427 m), the deepest pier
foundation (74 m below water surface at low tide), and the largest bored tunnel. The West crossing was the only major bridge
with two consecutive suspension spans.
The bridge, with its three major segments, is listed
on the National Register of Historic Places (NRHP). The Register’s comment is: “One of the
largest and most important historic bridges in the country”. In addition to its place on the NRHP, the
bridge received accolades from former President Herbert Hoover, speaking at the
ground-breaking ceremony in 1933: “This marks the physical beginning of the
greatest bridge yet erected by the human race.”
Hoover, who was originally a mining engineer, had followed the
development of the design of the bridge during his presidency. He was particularly interested in its effect
on unemployment in trying times—the Great Depression.
The entire bridge deserves its exalted historic
credentials, from the graceful sweep of the West crossing suspension structure,
through the YBI tunnel and viaduct, to the steel Cantilever Truss section, to
the through-truss and deck-truss spans.
The bridge was built in just 3½ years, at a cost
then estimated at $78 million. It was,
and still is, one of the greatest engineering achievements of the 20th
century.
Fig.
2. West crossing Fig.
3. East crossing (currently being replaced)
2.
General details,
design & construction
The Bay Bridge is a double decker. The original design featured 6 automobile
lanes on the top deck – 3 lanes in each direction. The bottom deck provided 3 truck lanes and 2
lanes (one in each direction) for an interurban commuter train. Around 1960, the arrangement was converted to
five eastbound lanes of traffic on the lower deck and five westbound lanes on
the upper deck.
The Bay Bridge was designed and built using
state-of-the-art techniques available in the 1930’s. For example, the engineers specified the
highest strength steel available for critical elements of the structures. Nickel (Grade 380 MPa) and silicon steel
(Grade 311 MPa) for the East crossing making up 62% of the total steel used there
and 72% of the Cantilever section. Even
the carbon steel used in this bridge was higher strength (Grade 255 MPa) than
normal. High-strength cable steel (Grade
828 MPa) was specified for the West crossing suspension cables.
The entire bridge required 151 593 tons of
structural steel. [1]
The Bay Bridge, and its neighbor, the Golden Gate
Bridge (completed at about the same time) represent the culmination of more
than 100 years of development of bridge engineering and construction in the
United States. To fully appreciate the
achievement of completing the construction in just 3½ years, consider the
technical level of construction at the time.
In addition to the lack of modern devices – heavy construction
equipment, vehicles, cranes, etc. - all steel connections were made using
rivets, requiring much more time and labor than modern high strength bolting
and welding. Compare this achievement
with the 12 years it is taking to build the current replacement bridge just for
the East crossing!
Amazingly, the 151 593 tons of steel used for the
entire Bay Bridge in 1936 is less than the tonnage Caltrans reported for
building just the superstructure of the new East crossing replacement [2]. A testament to the wisdom of the design for
the Bay Bridge West crossing is that, 62 years later, Japanese engineers chose
a very similar design for the towers of the longest bridge span in the world:
the Akashi-Kaikyo (or Pearl) Bridge.
3.
Loma Prieta earthquake
(1989)
The bridge’s East crossing was locally damaged during the Loma Prieta earthquake of 1989. A 15 m section of the top deck slipped off its support at an expansion joint; that end of the section collapsed onto the lower deck (Fig.4). One motorist was killed.
The bridge’s East crossing was locally damaged during the Loma Prieta earthquake of 1989. A 15 m section of the top deck slipped off its support at an expansion joint; that end of the section collapsed onto the lower deck (Fig.4). One motorist was killed.
It was subsequently decided to replace the entire
East crossing. Caltrans (California’s
Department of Transportation) dubbed the project an Earthquake Safety project,
an important decision because it meant only the pre-existing traffic capacity would
be restored.
After 7-8 years of discussion, planning and design, construction
on the new East crossing finally began in January 2002. The current estimate
for project completion is October 2013.
4.
West crossing improvements
and East crossing replacement
The West crossing (and its approach) underwent
seismic improvements in a 5-year project beginning in 1999, at a reported cost
of approximately $759 million. The
improvements included massive rollers installed between the roadway and bridge
supports and 96 new viscous dampers inserted at critical points to allow
movement. The bridge’s twin suspension
spans were strengthened by adding new steel plates and replacing half a million
original rivets with almost twice that many high strength bolts. New bracing was added under both decks and
all of the “laced” truss diagonals connecting the upper and lower road decks
were replaced. In total about 7710 tons of structural steel was added.
The East crossing replacement is currently under
construction. It is comprised of a
single tower, self-anchored suspension span and a 14 span (140m. each) concrete
skyway. The new crossing has added
shoulders and a bicycle lane. (Since
there is no bicycle lane on the West crossing, it will not be possible to bike
the entire length of the bridge). The
cost of replacing the East crossing is $6 417 M. Current plans are to demolish all of the
original East crossing structures from YBI to Oakland, and presumably recycle
whatever possible. Demolition is currently
estimated to cost at least $280 million. [2], [3]
5.
Traffic capacity
and population demographics
With only 5 traffic lanes in each direction, traffic
movement is greatly compromised, especially during commute hours.
In 1936 the Bay Area population was about 1 650 000. By 1990 it was about 6 024 000 and by 2010 it
was 7 150 000. The projected population
for 2025 is 8 880 000 (47% greater than in 1990).
Traffic growth has been even more rapid. When the bridge originally opened in 1936,
the traffic equivalent was 50 000 vehicles. By the late 1990’s, this critical highway link
carried about 280 000 vehicles on an
average day. So the growth in demand has
increased nearly 6-fold over the past 75 years.
Currently during commute hours it can take up to 30
minutes to drive the 7,1 km (from water’s edge to water’s edge) across the
bridge. That’s 14 km/h, and sometimes
it’s worse, especially if there is an accident on the bridge.
The idea of supplementing traffic capacity across
the bay is not new. Numerous studies
over the past 60 years have been conducted for new crossings (both bridges and
tunnels). None of these studies were
pursued, for environmental, political, cost and other reasons. However, these efforts show a great deal of continuing
interest in reducing the pressure on cross bay traffic.
6.
So what have we gained?
After more than 17 years of planning, design and
construction in connection with this new East crossing, along with the
improvements to the West crossing described above, we have a seismically
improved, 13,7 km long bridge (at a total cost over $7 billion). The entire Bay Bridge remains restricted
to five vehicular traffic lanes, essentially as it was when it was born in
1936. The inadequacy to handle traffic
demand was well known even when the new East crossing replacement was being
designed in the late 1990’s. And as time
goes by, the problem only gets worse!
7.
Proposed plans to
increase traffic capacity
Seeking a rational solution for this “problem”, some
of the possibilities are:
·
Expanding
BART’s (Bay Area Rapid Transit’s) underwater, cross-bay tunnel. BART has
already
reached maximum capacity of its twin tube system during peak commute times. Enlarging the underwater portion (and the above
ground track system) seems unrealistic.
·
Adding
more ferries. The Bay Bridge ended the ferry
system era long ago. And ferries imply
more automobiles to get to and from the water’s edge. Quite impractical.
·
Adding
a second bridge parallel to the existing Bay Bridge, a more practical idea already
proven in other cities around the world.
Considering these limited options, a second bridge
seems to be the most logical approach to solve the restricted capacity of the
existing bridge. And, given the fact
that the replacement of the old East crossing structure is nearing completion,
now is the time to begin planning and designing a completely new 2nd
SFO Bay Bridge alongside the present one using the retrofitted, old East crossing
structures. There are two major parts to
this proposal:
·
The
efficient retrofitting and realignment of the original, historic East crossing
structures.
·
The
design and construction of a new West crossing, alongside and complementing the
existing suspension bridge.
The most questionable elements of the original
(1936) East crossing are the foundations supporting most of the piers. These are timber piles driven into
questionable soil and should not be considered safe for reuse. It is believed, however, that the idea of
salvaging the 55 000 tons of already fabricated structures is a worthy
one. The best option for reuse of the
existing steel structures would be to build new foundations and piers alongside
the current ones, barging and lifting or sliding the existing superstructure on
to the new substructure and then reinforcing the existing superstructure to
meet current codes.
Fig.
6. Old truss spans – concept for creating continuity
Even if some of the existing structures need to be strengthened or reinforced, there is a good deal of value seen in the reuse of that steel, not to mention the possibility of converting significant demolition costs to a positive use – that of creating added bridge traffic capacity.
In contrast to past studies, this proposal differs
in that it looks to take advantage of the “abandoned” East crossing structures
by retrofitting and reusing them. This
represents some 55 000 t of fabricated
steel that served very well for decades, and is doing so currently. That
coupled with eliminating a good portion of the $280 million demolition budget
could easily represent in the range of $500 million “in the bank” to be
credited to construction of the new SFO Bay Bridge second crossing.
There are various options for increasing the structural
capacity of the systems involved. One
method is to interconnect the adjacent simple spans, converting them to a
continuous system. Members can be
strengthened by a judicious addition of plates, channels or other shapes to the
existing members, connecting them with bolts and/or welds. If necessary, compromised rivets can be
replaced with high strength bolts, as in the West crossing retrofit. Fig. 7. Cantilever truss section – reinforcing cable-stayed system
An interesting option would be to add a cable-stayed type of reinforcement system to the Cantilever truss section introducing “up-lift” forces at the tips of the cantilever arms. Another ingenious way to “increase” capacity is to reduce dead load by replacing existing heavy reinforced concrete slabs with lighter systems such as orthotropic steel decks. This approach was used very successfully in the early 1980’s on the redecking of the Golden Gate Bridge. This can reduce deck dead loads by up to 50-60 percent, “buying” extra structural capacity or otherwise relieving overstress situations. This technique would also make foundations more economical to construct.
An interesting option would be to add a cable-stayed type of reinforcement system to the Cantilever truss section introducing “up-lift” forces at the tips of the cantilever arms. Another ingenious way to “increase” capacity is to reduce dead load by replacing existing heavy reinforced concrete slabs with lighter systems such as orthotropic steel decks. This approach was used very successfully in the early 1980’s on the redecking of the Golden Gate Bridge. This can reduce deck dead loads by up to 50-60 percent, “buying” extra structural capacity or otherwise relieving overstress situations. This technique would also make foundations more economical to construct.
Of course, combinations of such approaches would be
in order. It is recognized that the use
of orthotropic steel decks and other “lightening” techniques would require
demolition of the concrete slabs now existing on the structures planned for
demolition (approx. 102 000 sq. m of 160 mm slabs) thus reducing the potential
savings from foregoing demolition. But
the other benefits, such as having to deal with much lighter elements to be
relocated, may well more than offset this issue.
It is obviously very important that decisions be
made and initial activities undertaken before the afore-mentioned demolition is
initiated. That demolition is scheduled
to begin in late 2013.
9.
New West crossing
(second bridge)
It is envisioned that the new West crossing would be
a double decker like its neighbor so that it would “flange up” with the
retrofitted (old) East crossing. That
would mean it would have 5 lanes in each direction (or 4 lanes plus a shoulder)
- the same width as the retrofitted East crossing. One scenario would feature twin suspension
structures placed end to end from San Francisco to YBI very similar to the
existing West crossing, but with two main spans of approximately 740 m, one
central span of approximately 760 m and two side spans of 370 m. A central anchorage separating the twin
bridges as in the 1936 bridge probably would not be necessary. Using the sophisticated analytical tools
available to today’s engineers, it is felt the bridge can be designed and built
without a central anchorage.
While the original bridge featured a tunnel and
viaduct through Yerba Buena Island separating the West and East crossings, the
idea for the new bridge would be to create a pier near the southern tip of
YBI. This pier would serve a combined function:
anchorage for the east end of the new West crossing and support for the west
end of a new, slightly curved, transition section between the pier and the west
end of the retrofitted, relocated cantilever truss structure.
An alternative to the above could be a cable-stayed
bridge with similar spans. There may be
other solutions, however, suspension and cable-stayed designs are the only ones
that have been shown to reasonably span farther than 700 m. Consideration of other systems would likely
require shorter spans necessitating more supports. This bridge should be designed to the highest
level of today’s achievements in bridge engineering and construction using all
modern technical ingenuity including orthotropic decks, high strength steel and
concrete, composite steel/concrete and the like. It is the authors’ strong opinion, the way to
achieve the best result in terms of beauty, efficiency, cost optimization and
construction time is to invite international concept competition by the best
bridge designers, worldwide. The winner
of such a competition should be invited to participate in design-build
competitions for the elements of the project.
10.
Cross Sections
of the Second Crossing with Traffic Lanes
Fig.
8. Traffic lane concept for Second Bridge Crossing
Because of the
relentless increase of population in the San Francisco Bay Area, and the
resulting pressure on traffic crossing the Bay, it is inevitable that a new
bridge will be needed to relieve that congestion. The abandonment of the old East crossing
offers an opportunity to double, or nearly double, the capacity of the
renovated SFO Bay Bridge. This paper
lays the ground work for doing that cost effectively by realigning and
retrofitting the 55 000 t of structural steel destined for abandonment and
demolition, sitting out there alongside the new and reconditioned bridge. It has been demonstrated here how this could
be done. But decision making and
planning must begin very soon—especially the decision not to demolish the steel
of the old East crossing.
11.
Discussions,
Final Comments and Conclusions
Constructability – A Second SFO
Bay Bridge Crossing is the only reasonable option to solve the heavy congestion
problems of the busiest highway bridge in Northern California, the question is
– is it possible to build such a bridge?
The
structure types proposed for the new West Crossing with maximum spans in the
740 to 760 m range are easily within the efficient capability of suspension and
cable-stayed bridges. Such systems have recently achieved spans up to and
exceeding 1,000 m.
26 suspension bridges have already spans longer than
1000 m, between the longest spans are
Akashi
Kaikyo Bridge, Japan, 1998, 1991 m,
Great Belt, Denmark, 1998, 1624 m and Xinomen,
China, 2009, 1650 m. Already
nine bridges have longer spans than Verrazano-Narrows and Golden Gate Bridge.
The cable-stayed
bridges have also passed 1,000 m length of span, the longest spans belong to Russky
Island Bridge, 2012, 1104 m, Sutong
Bridge, China, 2008, 1088 m, and Stonecutters Bridge, Hong Kong, as 1018 m.
Multiple consecutive spans are used today for both cable-stayed and
suspension bridges, for example – cable-Stayed Bridges; Millau Viaduct, France,
2004 with six interior spans, each 342 m, Rion-Antirion Bridge, Greece, 2004
with three interior spans each 560 m; multi-suspensions
bridges - Three-Tower Maanshan Yangtze Bridge, China, under construction,
scheduled completion – 2013 with two interior suspension spans each 1080 m
long.
Construction
Materials for the Superstructure – The steel for the Second Bay Bridge Crossing is 138,500 metric tons
based on “near-top efficiency”
including:
• 71,500 metric
tons steel for the 2nd West Crossing with a suspension bridge,
• 67,000 metric tons for the East Crossing, including
18,500 metric tons new or reinforced steel elements and 48,500 metric tons
reused original elements from the existing East Span (1936 year).
• Total new steel for the entire structure – 90,000
metric tons
Based on conservative parameters the steel will be 163,500 metric tons
including:
• 96,500 metric tons steel for the 2nd West
Crossing with a suspension bridge,
• 67,000 metric tons for the East Crossing, including
18,500 metric tons new or reinforced steel elements and 48,500 metric tons
reused original elements from the existing East Span (1936 year).
• Total new steel for the entire structure – 115,000
metric tons
For an alternative bridge system with cable-stayed bridge instead of a
suspension bridge the total steel is estimated between 148,900 and 170,400
metric tons, the increased quantities are from the West Crossing
cable-supported portion.
It is not a problem for the industry to produce and supply the steel
needed for the new bridge. The total new structural steel (including cables)
for the Bay Bridge Second Crossing – 102,000 tons (average) is 12% of the
yearly steel plate production in U.S. and only 1.5% of the yearly combined U.S.
production of plate and wide flange sections. These numbers are from the
production in the recent last years; the real capacity of the steel industry
exceeds well the recent production.
Importance
of Saving and Reuse of Existing Structures – Reusing of 55,000 tons of steel structures is a
significant saving of steel, energy, fuel, transportation, labor, time and also
is saving the environment. It is saving several operations each a large
consumer of energy.
- Collecting and transporting steel scrap to the mills;
- New steel mill production of 55,000 tons;
- Transportation of the 55,000 tons steel plate and shapes to the
manufacturers;
- Producing “in-shop” new 55,000 tons structures;
- Transporting these 55,000 tons structures to construction sites;
- Assembly and erection of 55,000 tons new structures.
To illustrate the transportation needs for moving the scrap to the mills, the new steel
to manufacturers and the new structures to the construction sides one should
consider that this will require about 2,750 (20-tons trucks) for each of this
operation, or about 8,250 trucks for the entire process.
Another way to illustrate what these 55,000 tons saving represents is to
consider that with this steel engineers and builders can deliver 120, 000
square meters (1,320,000 square feet) of bridges (with 750 meter spans or twice
longer than the SAS – Self-Anchored Suspension bridge), or 920,000 square
meters (9,9 Million SF) of typical Silicon Valley office buildings.
Advantages of the Second Bay Bridge Crossing:
1.
It
will resolve the extreme traffic congestion problems associated with the
original 1936 and improved current bridge, whose capacity has remained
essentially the same for 76 years.
2.
With
four or five traffic lanes in each direction, the Second crossing will increase
traffic capacity between San Francisco and Oakland by 80% to 100%. (Note: several options exist; 4 or 5 traffic
lanes, plus a shoulder and/or a bicycle lane with the ability to adjust
structural capacity by using orthotropic decks, etc.).
3.
It
will provide reserve crossing capacity should unforeseen problems such as
serious accidents, needs of repairs, earthquake, or other damage, occur.
4.
It
will redistribute traffic flow within San Francisco by way of more entry and
exit approaches, reusing previous routes from the removed in the 1990’s Interstate
280 to the Embarcadero.
5.
It
will greatly reduce the time required to cross the Bay especially in peak
traffic hours.
6.
It
will result in environmental savings from fuel saved by reducing “stop and go”
traffic during commute hours.
7.
It
will result in environmental savings by the reuse of 55 000 tons of steel
bridge structures – by reducing the need to produce, manufacture and transport this
quantity of new steel.
8.
It
can result in the possibility for bicyclists to ride from San Francisco to
Oakland and vice versa.
9.
The
large scale reuse of the existing East crossing structures will help in the development of new techniques to be
used for retrofitting many of the 150 000 deficient bridges in the U.S.
10. It will
capitalize on converting demolition costs to new construction, and reusing
already fabricated structures to the tune of $900 million.
11. With the
ingenuity required to adapt the older structures to today’s requirements and
the anticipated high level of design criteria and modern technique for the new
West crossing, it will contribute to the reawakening of the Art of American
Bridge Engineering.
What
shall be done?
The first step is to save the existing East Span of the Bay Bridge doomed
to be demolished. This will save immediately $240M, but the real value is
significantly more. The replacement bridge scheduled for opening by the end of
2013 costs $6.4 billion. This will be the real loss if the rare opportunity to
save the existing 55,000 metric tons structures and to reuse these structures
for a new Second Crossing is missed. Even if there is no sufficient funding available
for the Second Crossing in 2014 the planning and design should start
immediately to insure good preparation for faster and efficient construction.
12.
References
[1] UNITED STATES STEEL, “The San Francisco – Oakland
Bay Bridge”, 1936
[2] CALIFORNIA DEPARTMENT OF TRANSPORTATION, Bay
Bridge Project / Fact Sheets, baybridgeinfo.org
[3] CALTRANS “1st Quarter Report, 2013”, www.dot.ca.gov/baybridge/2013-1QReport.pdf
Subscribe to:
Posts (Atom)